Timetable
The council has prepared a Local Plan timetable setting out the key stages in preparing the Plan. You can view the timetable on this page and download a copy using the button below.
| Local Plan Stage | Date | Comments |
|---|---|---|
| Notice of Intention | 26 November 2026 | Formal notice that the Council intends to commence a new Local Plan. |
| Timetable | 26 November 2026 | Will be published alongside Notice of Intention. |
| Scoping Consultation | 4 January – 15 February 2027 | First consultation that covers detail on early plan content, community engagement and environmental assessment. |
| Gateway 1: Self-Assessment | 31 March 2027 | Formal commencement of 30-month process for Stevenage Borough Council. |
| Consultation: Proposed Local Plan Contents and Evidence | 16 June – 28 July 2027 | Will include Visioning document to focus the direction of the new Plan and maximise engagement in the Plan. |
| Gateway 2: PINS Advice | 6 December 2027 | The first time we meet the Planning Inspectorate to check in on progress and ensure the direction we are taking is in accordance with the soundness tests of the NPPF. |
| Consultation: Proposed Local Plan | 26 June – 18 September 2028 | This is the first time the public and stakeholders will be able to comment on the new version of the Local Plan. |
| Gateway 3: PINS Advice | 11 December 2028 | The second time we meet the Planning Inspectorate; at this time, the Plan will be scrutinised to ensure it meets the tests of soundness, iron out any outstanding issues and can be duly submitted for Examination. |
| Submission to Secretary of State | 12 February 2029 | Once Local Plan is deemed ready to submit to Government. |
| Examination in Public | Spring / Summer 2029 | Dependent on availability of Planning Inspectors and the scope of issues to be examined, though Gateways 2 and 3 will have provided opportunity to work through this in advance. |
| Adoption | 30 September 2029 | Completion of 30-month process. Followed by 6-week legal challenge. |